Tanks and Vessels
West Cumberland Engineering LtdWCEL delivered vessel manufacture for PPP across two phases including 14 additional tanks and vessels.
This project had a early contractor engagement phase which was held over a period of 5-6month period where PPP engaged with us over the vessel designs for the opportunity to highlight any downfalls/areas which would be unachievable and for recommendations for any changes/improvements to be implemented before issue for manufacture, it was also used to engage with the estimators for pricing of each vessel identified to be supplied by WCEL and for the production of any paperwork, procedures and processes to be produced and implemented. Following on from this and after agreement of cost and schedule we then moved into the manufacturing phase which kicked off in October 2020 and ran through until April 2022, the peak of which ran from August 2021 – March 2022.
Since commencement of the phase 1 works we were awarded a second phase of works for an additional 14 tanks and vessels in March 2021 of which the manufacture of one vessel commenced August 2021 which is currently awaiting sign off and release, the remaining works entered into production in April 2022 with an estimated completion date of February 2024 and we have since been awarded an additional vessel through a contract variation due to commence manufacture in July 2022 with an estimated completion date of November 2022.
The original order value of this second phase of works is £1,479,100.00 with an additional £67,108.00 awarded in the variation for the additional 15th vessel.