Pump frame/yoke assembly with pipework and specialist cabling for Sellafield: NWT re-engineered the frame to suit a revised pump, potted cables and passed witnessed FAT.

  • CA20 1PG, United Kingdom

NW Total Engineered Solutions was selected by Sellafield Ltd to manufacture and assemble a Pump Frame / Yoke Assembly, including associated pipework and specialist electrical cabling works. The project was awarded following a competitive tender process, recognising NW Total’s proven engineering capability, quality standards and delivery performance.

Key Project Highlights

Design Improvements

The client issued pump model had undergone a design change which affected the fit within the existing frame.

Engineering Review

NWT identified the changes and reviewed the impact on the assembly integration.

Modification Developed

Design modifications were developed to ensure teh new pump model fitted correctly and performed as intended.

Testing & Verification

Specialist electrical works including ‘Potting’ of cables and FAT testing were completed and witnessed / verified by the client.

Successful Delivery

The completed assembly was delivered with full documentation and ready for installation and use.