European Heathyards

Non contact desuperheater for a UK power station, in carbon steel and 13CrMo4-5 to BS1113, using TIG, MMA, SAW and explosive welding.

Non contact desuperheater assembly

Application: Heat transfer for superheated steam generation

Boiler: International combustion

Date of manufacture: 2009

Manufacturing spec: BS1113:1999

Manufacturing duration: 20-22 weeks

Materials: Body & Casing - Carbon Steel & 13Crmo4-5 Tube Bundle - 7/8" x 11 SWG - BS 3059 CFS 360

Welds procedures & processes: TIG, MMA, SAW, Explosive Welding

Heat treatment: Local & Furnace PWHT

Non destructive testing: 100% MPI, 100% U/T of Circ welds

Third party insurers: Royal & Sun Alliance

Hydro test: Full Hydraulic Test